VAK Russia 2.1.7 UDC 69.003 VAK Russia 2.1.14 UDC 004.9

METHOD FOR FORMALIZATION AND VALIDATION OF EMPLOYER'S INFORMATION REQUIREMENTS (EIR) IN A COMMON DATA ENVIRONMENT FOR RESIDENTIAL CONSTRUCTION PROJECTS Method for formalization and validation of employer's information requirements (EIR) in a common data environment for residential construction projects

Published in Construction production · Issue 3, 2026 · ELocator: CP0098 · Rubric: Original articles
DOI: https://doi.org/10.29039/2658-5340-2026-3-CP0098 · EDN: JRRFEL
Received: 24.07.2026 Accepted: 11.08.2026 Published: 29.09.2026 Language of publication: ru-RU
The purpose of this study is to develop a methodology for the formalization and validation of Employer’s Information Requirements (EIR) within a Common Data Environment (CDE) to improve data quality management and acceptance transparency in housing construction projects in the Russian Federation. The research methodology is based on the principles of the international standard ISO 19650, the concept of machine-readable Information Delivery Specifications (IDS), and Russian regulatory requirements (Decree of the Government of the Russian Federation No. 331, No. 614, GOST R 10.00.00.00-2023). The paper proposes a classification of EIR requirements suitable for formal verification, including completeness control, dictionary compliance, value ranges, and logical dependencies. A reference architecture for the validation function is developed, integrated into the CDE process loop through a system of statuses, versions of information containers, and a traceability matrix. The key methodological artifact is the "rule card", which ensures a clear link between a textual requirement, a verifiable criterion, and a managerial action. The approbation of the methodology on the example of envelope structures of a typical residential building demonstrated the possibility of translating disparate requirements into a reproducible verification cycle. The implementation of the proposed process scenario makes it possible to reduce the number of document returns, minimize subjective comments, and ensure the provability of the information model acceptance at the design stage.
building information modeling, common data environment, employer's information requirements; data validation, housing construction, automated checking, ISO 19650 standard
Text References

1. Postanovlenie Pravitel'stva Rossiyskoy Federatsii ot 05.03.2021 № 331 «Ob ustanovlenii sluchaya, pri kotorom obespechivayutsya formirovanie i vedenie informatsionnoy modeli ob"ekta kapital'nogo stroitel'stva» [On establishing a case in which the formation and maintenance of an information model of a capital construction object are ensured]. URL: https://www.publication.pravo.gov.ru/Document/View/0001202103100026 (accessed: 10.05.2026).

2. Postanovlenie Pravitel'stva Rossiyskoy Federatsii ot 17.05.2024 № 614 «Ob utverzhdenii Pravil formirovaniya i vedeniya informatsionnoy modeli ob"ekta kapital'nogo stroitel'stva i trebovaniy k formatam ukazannykh elektronnykh dokumentov» [On approving the Rules for forming and maintaining an information model of a capital construction object and requirements for the formats of these electronic documents]. URL: https://publication.pravo.gov.ru/document/0001202405170050 (accessed: 10.05.2026).

3. GOST R 10.00.00.00-2023. Edinaya sistema informatsionnogo modelirovaniya. Osnovnye polozheniya [Unified system of building information modeling. General provisions]. – M.: Standartinform, 2023. – 33 p.

4. SP 333.1325800.2020. Informatsionnoe modelirovanie v stroitel'stve. Pravila formirovaniya informatsionnoy modeli ob"ektov na razlichnykh stadiyakh zhiznennogo tsikla: svod pravil [Information modeling in construction. Rules for forming an information model of objects at various stages of the life cycle: code of practice]. – M.: Minstroy Rossii, 2020.

5. GOST R 57311-2016. Modelirovanie informatsionnoe v stroitel'stve. Trebovaniya k ekspluatatsionnoy dokumentatsii ob"ektov zavershennogo stroitel'stva [Information modeling in construction. Requirements for operational documentation of completed construction objects]. – M.: Standartinform, 2016.

6. Ziganshin A.M., Gadieva Z.I. Upravlenie informatsiey v srede obshchikh dannykh: problemy i perspektivy v rossiyskoy praktike [Information management in a common data environment: problems and prospects in Russian practice] // Stroitel'noe proizvodstvo [Construction Production]. – 2025. – No. 2. – P. 45–52.

7. ISO 19650-1:2018. Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) – Information management using building information modelling – Part 1: Concepts and principles. – Geneva: International Organization for Standardization, 2018.

8. ISO 19650-2:2018. Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) – Information management using building information modelling – Part 2: Delivery phase of the assets. – Geneva: International Organization for Standardization, 2018.

9. CEN/TR 18093:2024. Framework and Implementation of Common Data Environment solutions and workflow, in accordance with EN ISO 19650: Technical Report. URL: https://www.dinmedia.de/en/technical-rule/sng-cen-tr-18093/386957416 (accessed: 10.05.2026).

10. Wrzosek M., Owerko T., Rochel M., Kasznia D. Automating Compliance: Advanced Verification Techniques for Information Requirements in BIM Railway Projects // Geomatics and Environmental Engineering. – 2025. – Vol. 19, No. 3. – P. 63–89. – DOI:https://doi.org/10.7494/geom.2025.19.3.63. EDN: https://elibrary.ru/PVKUJO

11. Pauwels P., van den Bersselaar E., Verhelst L. Validation of technical requirements for a BIM model using semantic web technologies // Advanced Engineering Informatics. – 2024. – Vol. 60. – Art. 102426. – DOI:https://doi.org/10.1016/j.aei.2024.102426. EDN: https://elibrary.ru/WHHAGF

12. buildingSMART. Information Delivery Specification (IDS): buildingSMART International project. URL: https://technical.buildingsmart.org/projects/information-delivery-specification-ids/ (accessed: 10.05.2026).

13. Solihin W., Eastman C. Classification of rules for automated BIM rule checking development // Automation in Construction. – 2015. – Vol. 53. – P. 69–82. – DOI:https://doi.org/10.1016/j.autcon.2015.03.003.

14. Sacks R., Eastman C., Lee G., Teicholz P. BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers. – 3rd ed. – Hoboken: John Wiley & Sons, 2018. – 688 p. DOI: https://doi.org/10.1002/9781119287568

15. Scottish Futures Trust. PIM Data Exchanges and Validation (BIM Level 2 Guidance). URL: https://bimarchive.scottishfuturestrust.org.uk/level2/sfthub/stage/5/task/15/pim-data-exchanges-and-validation (accessed: 10.05.2026).

16. University of Cambridge, Centre for Digital Built Britain. Exchange Information Requirements (EIR) Guidance. URL: https://www.cdbb.cam.ac.uk/files/eir_guidance.pdf (accessed: 10.05.2026).

17. GOST R 10.0.02-2019/ISO 16739-1:2018. Sistema standartov informatsionnogo modelirovaniya zdaniy i sooruzheniy. Otraslevye bazovye klassy (IFC) dlya obmena i upravleniya dannymi ob ob"ektakh stroitel'stva. Chast' 1. Skhema dannykh [System of standards for building information modeling. Industry foundation classes (IFC) for exchange and management of construction object data. Part 1. Data schema]. – M.: Standartinform, 2019.

18. GOST R 10.0.03-2019/ISO 29481-1:2016. Sistema standartov informatsionnogo modelirovaniya zdaniy i sooruzheniy. Informatsionnyy menedzhment v stroitel'stve. Spravochnik po obmenu informatsiey. Chast' 1. Metodologiya i format [System of standards for building information modeling. Information management in construction. Information exchange manual. Part 1. Methodology and format]. – M.: Standartinform, 2019.